There are situations when one item gathers multiple metrics at a time or it even makes more sense to collect related metrics simultaneously, for example:
To allow for bulk metric collection and simultaneous use in several related items, Zabbix supports dependent items. Dependent items depend on the master item that collects their data simultaneously, in one query. A new value for the master item automatically populates the values of the dependent items. Dependent items cannot have a different update interval than the master item.
Zabbix preprocessing options can be used to extract the part that is needed for the dependent item from the master item data.
Preprocessing is managed by a preprocessing manager
process, along with worker threads that perform the preprocessing steps. All values (with or without preprocessing) from different data gatherers pass through the preprocessing manager before being added to the history cache. Socket-based IPC communication is used between data gatherers (pollers, trappers, etc) and the preprocessing process.
Zabbix server or Zabbix proxy (if host is monitored by proxy) are performing preprocessing steps and processing dependent items.
Item of any type, even dependent item, can be set as master item. Additional levels of dependent items can be used to extract smaller parts from the value of an existing dependent item.
A dependent item depends on its master item for data. That is why the master item must be configured (or exist) first:
All mandatory input fields are marked with a red asterisk.
Click on Add to save the master item.
Then you can configure a dependent item.
All mandatory input fields are marked with a red asterisk.
The fields that require specific information for dependent items are:
Type | Select Dependent item here. |
Key | Enter a key that will be used to recognize the item. |
Master item | Select the master item. Master item value will be used to populate dependent item value. |
Type of information | Select the type of information that will correspond the format of data that will be stored. |
You may use item value preprocessing to extract the required part of the master item value.
Without preprocessing, the dependent item value will be exactly the same as the master item value.
Click on Add to save the dependent item.
A shortcut to creating a dependent item quicker can be accessed by clicking on the button in the item list and selecting Create dependent item.
In the item list dependent items are displayed with their master item name as prefix.